Navitech has just completed the installation of concrete wall reinforcement in the starting chamber for the TBM machine. We completed the assembly of 550 tons of steel within 3 weeks! All works were completed ahead of schedule, meeting the expectations of the purchaser.
I-st level




II-nd level

Job completed


In the meantime, we also performed a number of additional works.
We have finished the production of various types of steel supports and a cradle for the TBM machine with a total weight of 150 tons.



We are waiting for the next challenge 🙂